I need to process a number of files into a multipage workbook. To do this I have the following process

Files concatenated into one file "Concat.csv" which is passed through PivotToColumnsDelimited. However PivotToColumnsDelimited started processing before Concat.csv was still being read the result was truncated so I used a PostJob component to ensure concat was fully written before pivoting.

 

Is there a way to delay components from starting  until previous process has completed?

 

Thanks

Mick

 

 

1 ACCEPTED SOLUTION

Accepted Solutions
Twelve Stars

Re: Wait until single subjob completes

better of course attache Your Job screenshot

 

as I can guess You just need connect Components with OnSubJobOk trigger

https://help.talend.com/reader/QrWkwPvKmKybs~JNLeBt3Q/U7rkvi010m8mzVYNXSkH2Q

-----------
2 REPLIES
Twelve Stars

Re: Wait until single subjob completes

better of course attache Your Job screenshot

 

as I can guess You just need connect Components with OnSubJobOk trigger

https://help.talend.com/reader/QrWkwPvKmKybs~JNLeBt3Q/U7rkvi010m8mzVYNXSkH2Q

-----------
Six Stars

Re: Wait until single subjob completes

Thank you,