Five Stars

Talend Scheduler, How to make one Talend Job to run after the successful execution of another talend job

We are having challenges in defining end to end flow in Talend scheduler today. As there is no option for us to schedule the Talend Jobs (Using Job dependent option rather than time dependent), we are doing this inside the talend job using onSubJobOK option. This option however makes the Talend job more complected.

 

Is there any option to schedule one Talend job dependent on another talend job ?

1 REPLY
Employee

Re: Talend Scheduler, How to make one Talend Job to run after the successful execution of another talend job

Hi

In the context of Talend Integration Cloud, you can use Execution Plans that are a way implement sequences of jobs.

Regards
JG