One Star

Running multiple tasks asynchronously

Hi,
I have a SSIS job I want to rewrite as a TOS DI job. I t has 4 tasks which run asynchronously and only when all 4 taks have completed do the flow move to the next part of the jobs process.
Is this possible? If so is there any resource I can read more about this? I looked/googled and didn't come up with much.
Thanks, Dave.
2 REPLIES
One Star

Re: Running multiple tasks asynchronously

Hi,
You can put 4 tasks into 4 subjobs.
In a main job,you put 5 tRunjobs et 1 tpostjob,
4 tRunjob connect to 4 task, tpostjob connect to the rest runjob which contains your other process.
It may work.
Best regards
Seventeen Stars

Re: Running multiple tasks asynchronously

The feature running jobs parallel is a Enterprise feature and only available in the none open versions.
If you need your 4 jobs simultaneously you need an external job scheduler which provides this feature (try JobScheduler from SOS Berlin). In this way you can use the return codes to run different task for different return codes.