Seven Stars

TAC - Stop/ suspend a job for 1 day manually

Hi All,

 

I am very new to TAC, 

I have Operation manger Role in TAC,

 

I need to suspend/ stop a job for a day , as per request, and resume it again back to regular schedule after 1-2 days.

can anyone tell me process.

 

Thanks,

Sachin

1 ACCEPTED SOLUTION

Accepted Solutions
Seven Stars

Re: TAC - Stop/ suspend a job for 1 day manually

If you click on the job, at the bottom of the screen you can find the "Triggers" button, clicking this will open a menu that will show all triggers that will run that job. Select "Pause Trigger" to pause each trigger on that job.  This will prevent it being run until you go back and hit "Resume Trigger"

3 REPLIES
Seven Stars

Re: TAC - Stop/ suspend a job for 1 day manually

If you click on the job, at the bottom of the screen you can find the "Triggers" button, clicking this will open a menu that will show all triggers that will run that job. Select "Pause Trigger" to pause each trigger on that job.  This will prevent it being run until you go back and hit "Resume Trigger"

Seven Stars

Re: TAC - Stop/ suspend a job for 1 day manually

Thanks @evansdar, I will perform mentioned steps.

Moderator

Re: TAC - Stop/ suspend a job for 1 day manually

Hello,.

For more information, please refer to online user guide aboutTalendHelpCenter: Scheduling an execution plan

and TalendHelpCenter: Scheduling execution tasks.

Best regards

Sabrina

--